Finvest
LNT Regulated Utilities · Utility · Data centers · Clean energy · Thesis updated July 19, 2026

Data centers can power Alliant, if projects land

01 Running thesis

Data center load meets utility execution

Alliant has a simple story with hard execution behind it. The company has about 3.4 GW of contracted data center demand, which management says is more than a 60% increase in current peak demand. That gives Alliant a clearer need to build power plants, wires, and related assets.

The latest filings made the plan easier to judge. IPL filed for an approximately 720 MW simple-cycle natural gas plant in Linn County, Iowa. The Iowa regulator also approved advance rate-making principles for up to 1,000 MW of new wind generation. Rate-making means the rules that decide how a utility can recover costs from customers.

The bull case is that this load growth supports Alliant's 5-7% long-term EPS growth target. Iowa is the center of the story because it has better land availability, transmission access, and gas access inside Alliant's service area. If projects move on time, the company can grow its rate base, which is the pool of assets regulators allow it to earn a return on.

The bear case is not that demand is missing. It is that Alliant must build a lot, fund a lot, and win approvals on time. The stock also does not look cheap in Finn's scoring, and financial health is a weak spot. That means even a good growth story needs clean execution.

May 2026Alliant added clarity to the buildout plan. IPL filed for an approximately 720 MW Iowa gas plant, the IUC approved advance rate-making principles for up to 1,000 MW of new Iowa wind, and a new 370 MW Iowa data center agreement lifted contracted demand to about 3.4 GW.
Feb 2026A QTS data center project moved from Wisconsin to Iowa with a new service agreement, keeping the growth plan on track. Management also shifted near-term generation planning toward quicker simple-cycle gas plants.
Aug 2025Alliant showed more progress in its large load pipeline by discussing a QTS agreement in principle and a high confidence level for mature opportunities. The update made the data center growth runway more visible.
May 2025The company announced 2.1 GW of fully executed data center service agreements and raised the 2025-2028 capital plan by about $600 million. The main risk shifted from finding demand to executing the bigger buildout.
Feb 2025The initial thesis framed Alliant as a regulated utility with clean energy growth and rising data center demand. It also flagged weather, regulation, and project execution as the key risks.
02 Business model

Paid to build and serve load

Alliant is a regulated utility holding company. It earns money by selling electricity and natural gas in Iowa and Wisconsin, then earning allowed returns on approved utility investments. Most of the business is steady, because customers need power and heat in normal times.

The growth model is changing. New hyperscale data centers need huge amounts of electricity, and Alliant now has five executed data center agreements representing about 3.4 GW of contracted demand. To serve that load, it plans to add flexible generation, including simple-cycle gas plants, batteries, wind, and solar.

Simple-cycle gas plants are quicker-to-build power plants that can start fast when the grid needs capacity. That matters because data center customers have strict timelines. Iowa's strong wind resources help with energy supply, while gas plants and batteries help with reliability.

The model can break if costs rise, projects slip, or regulators reject the timing and cost recovery. Mild weather can also hurt earnings by lowering energy use, as it did in 2024 with a $0.15 per share headwind compared with normal weather.

03 Product portfolio

Power, gas, and new capacity

Cash cow

Electric utility service

Electric service is the core business. It serves retail and wholesale customers and is where data center demand creates the biggest growth need.

Steady

Natural gas utility service

Gas service adds a more traditional utility revenue stream in Iowa and Wisconsin. Demand can swing with winter weather.

Growth engine

Data center electric service agreements

Alliant has five executed agreements totaling about 3.4 GW of contracted demand. A new 370 MW Iowa agreement signed in April 2026 added to that base.

Growth engine

Wind and solar generation

The company completed about 1.5 GW of solar projects in 2024 and has approval for advance rate-making principles for up to 1,000 MW of new Iowa wind. These assets support the cleaner energy shift.

Growth engine

Simple-cycle natural gas generation

IPL filed for an approximately 720 MW simple-cycle gas plant in Linn County, Iowa. These plants are built for speed and grid reliability, not constant power output.

Option

Coal generation retirement plan

Alliant continues to phase out coal-fired generation. The shift can lower emissions over time, but it also requires replacement capacity that works when customers need power.

04 Business segments

Two state utilities

Interstate Power and Light48%growing fast
Wisconsin Power and Light52%modest

Mix uses Q1 2026 subsidiary revenue from the 10-Q: IPL at $561 million and WPL at $600 million. Shares are normalized to the two main utility subsidiaries, since non-utility revenue was small.

05 Risk factors

What could break the plan

Iowa gas plant delay

High impact · Medium odds

IPL needs approval for the approximately 720 MW Linn County simple-cycle gas plant. A delay could make it harder to match power supply with data center timelines. It would also raise questions about whether extra capacity must be filed later.

We watchThe IUC decision expected in the first quarter of 2027.

Large load does not ramp as planned

High impact · Medium odds

The growth case depends on data center customers taking power on schedule. Alliant has about 3.4 GW of contracted demand, but contracts still need construction, interconnection, and customer buildout to turn into actual load. Any slowdown would weaken the capital plan story.

We watchUpdates on the five executed data center agreements and the full load ramp expected by 2030 for the new 370 MW Iowa customer.

Capital plan funding pressure

High impact · Medium odds

Building new generation and grid assets takes a lot of money. Management previously said incremental capital spending could be funded with roughly 40% to 50% new common equity. That can dilute shareholders if the stock price is weak or project needs grow.

We watchAny capital plan update, equity issuance plan, or change in the 2025-2028 spending outlook.

Weather earnings hit

Medium impact · Medium odds

Alliant is sensitive to temperatures because heating and cooling drive energy use. In 2024, mild temperatures created a $0.15 per share earnings headwind versus normal weather. A repeat could offset some of the growth from new load.

We watchQuarterly weather-normalized earnings commentary and heating or cooling degree day variance.

IRA tax credit changes

Medium impact · Medium odds

Renewable and storage project economics depend partly on tax credits. Management has warned that removing credits would increase customer costs. Alliant has safe-harbored 100% of renewable and energy storage capital spending in its plan through 2028, which helps but does not remove policy risk.

We watchFederal changes to Inflation Reduction Act tax credits and management's comments on safe-harbored projects.

MISO capacity rule changes

Medium impact · Medium odds

Management has referenced MISO accreditation changes, but the net impact on capacity needs is still an open question. Accreditation decides how much reliability credit each power resource gets. If credits fall, Alliant may need more capacity than investors expect.

We watchCompany details on MISO accreditation and any change to required generation capacity.
06 Quick answers

In one breath

Why are data centers important for Alliant Energy?

Data centers use very large amounts of electricity. Alliant says its about 3.4 GW of contracted data center demand equals more than a 60% increase in current peak demand, which supports a larger utility investment plan.

Is Alliant Energy mainly an Iowa company or a Wisconsin company?

It serves both states through IPL in Iowa and WPL in Wisconsin. The newest large data center growth is more concentrated in Iowa because management points to better land, transmission, and gas access there.

Why is Alliant building gas plants if it is adding wind and solar?

Wind and solar provide clean energy, but data centers also need reliable capacity when the grid is tight. Simple-cycle gas plants and batteries can come online faster and help cover peak demand.

What is the main investor concern with LNT?

The demand story is clearer than before, but the company must still build, finance, and win approval for many projects. Finn's weaker valuation and financial health scores mean the market already gives Alliant limited room for mistakes.